Water Main Installation on 63 Street

Project Phase – Completed

Project Limits

Along W 63 Street (SR 907) from La Gorce Drive to Indian Creek Drive.

Scope of Work

  • Replacing water mains and service lines
  • Installing fire hydrants

Project Timeline

Estimated Start Date: January 2016
Estimated Completion Date: Winter 2017

Project Team

This project is managed by the City’s Public Works Department.

City of Miami Beach Acting City Engineer
Luis Soto, P.E.

City of Miami Beach City Project Manager
Jose Rivas, P.E.

Design Criteria Professional
Milian, Swain & Associates, Inc.

Engineer of Record
Arsenio Milian, P.E.

Contractor
David Mancini & Sons, Inc. (DMSI)

Public Information Officer
Leydis Colomina Power, DMSI
Phone: 786.484.9158 Email: lcolomina@dmsi.co