Sunset Islands III and IV
Project Phase – Construction
Project Limits
- Sunset Islands III and IV
Scope of Work
Infrastructure Improvements:
- Lining of the sanitary sewer main including structures and laterals
- New water main and electronic water meters
- Installation of new storm water drainage system and pump stations
- Cleaning and lining of the existing drainage outfalls
- Overhead utility (FPL, ABB and ATT) undergrounding
- New conduits, wire and service point for the existing street lights
Roadway Improvements:
- Roadway reconstruction
- Concrete valley gutter
- Sidewalks extension along portions of Sunset Drive
- Brick paver speed tables
- Pavement marking and signage
- Tree planting
- Driveway and swale harmonization
Project Timeline
Start Date – Summer 2015
Completion Date – This project is in close out.
Project Team
City of Miami Beach Senior Capital Project Coordinator
Mina Samadi
City of Miami Beach Capital Project Coordinator
Pilar Caurin Tortajada
Public Information Specialist
Lauren Firtel
LaurenFirtel@miamibeachfl.gov
305.673.7071