Normandy Isle Phase II

Project Phase – Design
Project Limits

Marseille Drive from Trouville Esplanade to Rue Notre Dame
Calais Drive between Trouville Esplanade and Rue Bordeaux
Project Scope

Lighting Improvements, installation of 15 new pedestrian street lights
Project Timeline

Start date for construction – January 2017
Completion date – Spring 2017

Project Team

City of Miami Beach Senior Capital Project Coordinator

Mina SamadiCity of Miami Beach Capital Project Coordinator
Elizabeth Estevez

Contractor – Solares Electrical Services, Inc.

CIP Public Information Specialist
Lauren Firtel
Email: Laurenfirtel@miamibeachfl.gov
Phone: 305.673.7071