La Gorce And Lakeview
Project Phase - Assessment
The City of Miami Beach Public Works Department will contract up to three firms to design plans and construct a Right of Way Infrastructure Improvement Project for the La Gorce and Lakeview neighborhoods. This project is currently awaiting on the completion of the Jacobs Engineering project priority assessment.
Project Limits:
- Northern limit: La Gorce Island
- Eastern limit: La Gorce Country Club
- Southern limit: Surprise Lake
- Western limit: Biscayne Bay
The project is expected to be broken into three smaller areas where up to three different main contractors may be working:
- La Gorce Island entrance to 59 Street, including 62 Street
- 59 Street to 51 Street
- 51 Street to Surprise Lake
Scope of Work:
Infrastructure Improvements:
- Installing new stormwater drainage system
- New pump stations currently identified at:
- Fisher Park
- 56 Street, street end
- South side of 63 Street bridge
- Replacing water mains and service connections
- Sanitary sewer work including three lift stations (56 Street, street end; 51 Street and Alton Road; and 63 Street and Alton Road) and relocating service connections to front of properties (not homes on Alton Road).
Roadway Improvements:
- Elevating roadway
- Constructing new curb, gutter and sidewalk at new elevation
- Harmonizing the roadway to existing driveways
- Placing new signage and pavement markings
- Installing new street lighting
- Adding a dedicated bicycle lane on 51 Street
Project Team
City of Miami Beach Acting Engineer
Luis Soto, P.E.
City of Miami Beach Senior Capital Project Coordinator
Mina Samadi, P.E.
Design-Build Team(s)
TBD
Public Information
Heather M. Leslie, HML Public Outreach
Ph: 305.905.5876
Email: heather@hmlpublicoutreach.com