Section 2 A 7. Dewatering
SECTION 2 RIGHTS-OF-WAY CONSTRUCTION REQUIREMENTS A. Rights-of-Way Permits and Procedures 7. Dewatering Permit requirements for Dewatering: a) 4 sets of site plan drawn to scale (11โณx17โณ Minimum size), to include right-of-way dimensions identifying property lines, ground water discharge location into designated storm inlet structure/body of water.
b) Provide current copy of Certificate of Insurance Liability/Workmenโs Compensation coverage to be approved by the Cityโs Risk Management Division
c) Provide four sets of the Engineer of Record, signed/sealed dewatering plan $500.00 minimum bond. The determination will be made by Public Works Engineering Photographs of existing sidewalk/curb/gutter/asphalt pre-existing conditions.
d) Provide copy of DERM approved dewatering permit package
e) Provide Copy of *F.D.O.T. approved permit package to include roadway/ lane closure approval f) Maintenance of Traffic Plant (M.O.T.) An off-duty Miami Beach police officer or F.D.O.T. Certified g) Flagman may be required. A determination will be made by Public Works Engineering.
|