Section 2 A 5. Construction Dumpster Roll Off Placement

Construction Dumpster-Roll-off Placement

SECTION 2 RIGHTS-OF-WAY CONSTRUCTION REQUIREMENTS

A. Rights-of-Way Permits and Procedures

5. Construction Dumpster-Roll-off Placement

Permit requirements for Construction Dumpster- Roll-off Placement:

a) Four (4) sets of site plan drawn to scale,  (11″x17″ minimum size), to include Right-of-Way dimensions identifying property lines.

b) Dumpster placement requires location approval by Code Compliance Department prior to Right-of-Way Permit issuance.

c) Provide current copy of Certificate of Insurance Liability//Workmen’s Compensation coverage to be approved by the City’s Risk Management Division.

d) $500.00 minimum sidewalk bond or security deposit

e) Photographs of existing sidewalk/curb/gutter/asphalt pre-existing conditions

f) Proof (receipt) of parking meter space purchased from City of Miami Beach Parking Enforcement Division

g) Maintenance of Traffic Plan (MOT). An off duty Miami Beach Police officer or F.D.O.T. Certified Flagman may be required. A determination will be made by Public Works Engineering.